Auditors found no noncompliance in San Rafael’s use of Measure A transportation sales-tax interest funds during fiscal 2025-26, according to a staff report prepared for the Transportation Authority of Marin’s Nov. 16 oversight committee meeting.

The review covered all Measure A interest funds allocated and spent by the city that fiscal year. The official meeting packet identifies bicycle and pedestrian pathway maintenance as the funded activity. Staff reported that no follow-up action was needed.

San Rafael was one of five recipients selected for the audit cycle. The TAM Board approved the list July 23.

Moss, Levy & Hartzheim conducted the audits. An Aug. 18 workshop preceded meetings with recipients beginning in September. Draft results went to TAM staff in early November.

Four audits had no findings. The exception involved San Anselmo’s Safe Pathways to School beacon project, where staff time was billed at a rate that did not reflect actual payroll costs, contrary to the funding agreement.

San Anselmo submitted a corrected invoice. TAM staff said billing rates would receive closer checks during program and finance reviews. No additional corrective action was needed, according to the report.

The other audits covered Tiburon’s pavement rehabilitation funding, Marin Transit’s local transit operations and capital needs, and All City Management Services’ crossing guard program. None had findings.

The memo was prepared by Executive Director Anne Richman, Director of Finance and Administration Melanie Purcell and Principal Accountant Emily Tong.

TAM staff anticipated board review and acceptance of the audit reports Dec. 17.

U.S. 101 transit lane pilot remains in planning

The packet also included an update on a proposed southbound U.S. 101 part-time transit lane from De Long Avenue in Novato to North San Pedro Road in San Rafael.

TAM and consultant Kimley-Horn and Associates are working with Caltrans on a project initiation document. Staff review of a draft is expected in December, with Caltrans approval anticipated in mid-2027. The packet’s schedule identifies 2028 for the start of environmental studies.

A technical advisory committee met Sept. 24 and agreed to study two alternatives: operating under existing corridor conditions and operating with ramp metering activated.

The report says significant additional funding would be needed to move the project into construction.