Marin County Parks opened a public comment period on its plan to replace the deteriorated dock at Buck's Landing on Gallinas Creek.
The California Environmental Quality Act (CEQA) comment window runs from Monday, Nov. 23, at 8 a.m. through Monday, Dec. 28, at 5 p.m., according to the county's project page. The property on the southern bank of Gallinas Creek provides public access to San Pablo Bay.
The county prepared a draft Initial Study/Mitigated Negative Declaration (IS/MND) for the Buck's Landing Dock Replacement Project. The environmental document analyzes potential impacts and proposes measures to reduce them. Marin County Parks said it will consider comments before finalizing the study.
What the project would build
The plan calls for a new pile-supported pier, an accessible gangway, a floating dock, a raised boardwalk, signage, an accessible parking stall and a walkway to the existing restroom and picnic area. The rebuilt pier and dock would let boaters launch without walking through mudflats and reach Gallinas Creek at low tide.
The existing pier was in severely degraded and unsafe condition. After acquiring access rights, Marin County Parks deemed it a public hazard and closed it.
A decades-long effort
Marin County Parks purchased the property in two phases: a 30-acre parcel in 2020 and a 7-acre parcel in 2022. A $500,000 grant from the California Coastal Conservancy, funded through the Greenhouse Gas Reduction Fund, helped pay for the first acquisition.
The site dates to the 1800s, when it served the Remillard Brick Company. Recreational boaters, fishermen and hunters have used it since at least the 1940s, according to the county.
Neighborhood input shaped the design
Several community groups helped shape the project. In December 2025, Marin County Parks staff met on-site with members of the Santa Venetia Neighborhood Association to review 30 percent design plans. Residents stressed the importance of keeping informal small-craft launching from the ramp.
In August 2022, the agency partnered with Voces del Canal and Canal Alliance to host a bilingual guided hike and site visit. Participants discussed amenities such as picnic tables, barbecues and expanded kayaking and small-boat programs.
The Parks & Open Space Commission reviewed the feasibility study and 30 percent design drawings at a meeting in March 2025. The Marin Conservation League's Parks & Open Space Committee provided feedback on wildlife signage, seasonal access restrictions and species protection in November 2025.
How to comment
Residents can review the draft environmental study and submit feedback through the county’s public comment form before the Dec. 28 deadline.
The project requires permits and other approvals from federal and state agencies, including the U.S. Army Corps of Engineers and the San Francisco Bay Conservation and Development Commission, before construction can begin.